Reconstruction of Town Line Road to begin



Beginning on or about Monday, Sept. 13, the reconstruction of Town Line Road will begin.

Construction activities have been divided into two phases. Phase 1: South Washington Street to Red Stone Street (Southington). The first phase has an expected substantial completion date of December. Phase 2:  Red Stone Hill to 100-feet north of Red Stone Street (Southington). The second phase will begin in April 2022 and has an expected substantial completion date of June 2022. The 100-foot gap between the two phases will be reconstructed by the state DOT as part of the multi-use path project.

The Town of Plainville has retained Tobacco & Sons Builders of Bristol to reconstruct Town Line Road. Construction activities will involve drainage upgrades, excavation and replacement of the existing roadway base material, repaving and other associated improvements.

Project specific travel delays can be expected on Town Line Road and Red Stone Hill. Alternating one-way traffic within the work zone will be implemented while certain construction activities proceed. Thru traffic is urged to seek alternative routes. Access to businesses along Town Line Road will be maintained during construction.

plainvillect.com



Advertisement
With local school, politics and coronavirus news being more important now than ever, please help our newsroom deliver the coverage you deserve. Please support Local news.

More From This Section

Advertisement